Skip to content

Technical · 10 min read

Installation Guide: Pit vs Ramp

Floor configuration is a one-time civil decision. Get it wrong and you live with it for 15 years.

The two options, briefly

A roll-in rack washer requires a flat transition between the kitchen floor and the chamber floor. Two civil configurations achieve this:

  • Pit installation: machine drops into a recessed floor pit so the chamber floor is flush with the existing kitchen floor. Trolleys roll level in and out.
  • Ramp installation: machine sits on the existing floor; a ramp on each side bridges the chamber threshold. Trolleys roll up the ramp into the chamber.

Pit installation — when to choose

Pit installation is the premium option, used in 70% of professional commissary installs. Advantages:

  • Trolleys load level — no ramp resistance, no risk of tipping on transition
  • Worker ergonomics — no lifting or pushing up a ramp
  • Cleaner aesthetic — no protruding ramp tripping hazard
  • Faster cycle throughput — load/unload is 20% faster than ramp

Disadvantages:

  • Civil work required: floor saw-cut, concrete excavation, drain re-routing, structural reinforcement of pit floor
  • One-time cost: $3,000–$8,000 depending on building type
  • Drain depth: pit drain must connect to lower-level building drain (sometimes requires sump pump)
  • Cannot be undone — building modification permanent

Pit dimensions for PTW-1900: 2,000 × 2,200 mm pit, 250 mm depth. Pit floor must be sloped 1:50 toward the chamber drain. Sealed concrete or stainless pan finish required.

Ramp installation — when to choose

Ramp installation is the operationally-flexible option, used in 30% of installs (rental kitchens, short-lease facilities, second-floor commissaries where pit excavation is impossible).

Advantages:

  • No civil work — machine sits on existing floor
  • Relocatable — machine can move to a new building
  • Shorter project timeline (2 weeks vs 4 weeks)
  • Lower total install cost

Disadvantages:

  • Trolley pushing up the ramp — ergonomic load on operator
  • Heavy loaded trolleys (200+ kg) may need a winch on the ramp
  • Ramps are 1.2 m long each side — total footprint 2.4 m longer than pit install
  • Ramp transition slows cycle throughput marginally

Ramp specifications: stainless steel ramp at 1:8 slope (12.5%), anti-slip diamond plate or grooved surface, 250 mm height, removable for chamber service access. V-TAI ships ramps as standard accessory.

Drainage considerations

The PTW-1900 produces:

  • Pre-rinse drain: 5 L per cycle, dumped fast
  • Wash tank dump: 80–100 L every 5–6 cycles (~once per hour)
  • Booster rinse drain: 30 L per cycle (~30 L/hour peak)

Total peak drain flow: approximately 120 L/hour sustained with brief 200 L/hour peaks during wash-tank dumps. Drain pipe spec: 2" (50 mm) minimum, slope 1:50 toward building stack. Hot-water-rated PVC (Class 6) or stainless tubing.

Critical: route drain through a properly-sized grease trap. Rack-washer effluent carries emulsified food fat that will clog cold building stack if no grease trap. Code requirement in U.S., EU, and most Asian jurisdictions.

Ventilation

During the 82°C rinse stage, the chamber vents steam. Total steam vent volume: approximately 60–80 m³/hour per machine. Two ventilation options:

  • Direct duct vent: 320 mm (12") duct from chamber top to exterior. Code-mandated dampers and grease traps. Standard solution for new installs.
  • Steam condensation hood: condenses exhaust steam and recovers heat to incoming water. Cuts visible exhaust plume by 80%, recovers ~10% energy. Recommended for installs near residential areas or with limited duct routing.

Utility connections

ServiceSpecification
Electrical (electric version)380V / 3-phase / 50Hz / 100 A breaker. 60Hz available on request.
Electrical (steam version)380V / 3-phase / 50Hz / 16 A breaker.
Water inlet3/4" connection, cold water, 2–4 bar pressure
Steam inlet (steam version)1" connection, 8–10 bar saturated steam
Drain2" connection, hot-water rated, slope to building stack
ExhaustØ480 mm duct to roof or steam-condensation hood

Floor space and clearance

  • Machine footprint: 1,845 × 2,050 mm
  • Door swing (double-leaf): 1,200 mm both sides
  • Recommended clearance: 1 m service access on left, 1 m on right (for door opening), 600 mm rear (for utility connections)
  • Total install footprint: approximately 3,500 × 4,000 mm with door swing and service access

Pre-installation checklist

  1. Confirm building electrical capacity (70 kW for electric version)
  2. Confirm building water supply pressure and flow (3/4" line, 2 bar minimum)
  3. Confirm drain capacity (2" hot-water-rated, grease trap, building stack)
  4. Confirm steam capacity (steam version only — 35 kg/hr saturated)
  5. Confirm ventilation route (320 mm duct or steam hood)
  6. Decide pit vs ramp installation (civil work plan)
  7. Confirm trolley dimensions to verify chamber fit
  8. Confirm floor levelness within ±2 mm over 4 m² (machine footprint)

V-TAI provides a free site-assessment service when you request a quote.

Related reading

Ready to Modernize Your Plant's Cleaning?

Get a configuration-specific quote within 12 business hours. Custom rack dimensions, electric or steam heating, full installation specs included.